A further delay to the ASX’s long-running project to replace critical infrastructure has sparked frustration among stockbrokers, after the market operator said it did not expect the new system to go live before late 2024.
The ASX on Wednesday announced the latest in a series of delays to a major project to replace its ageing clearing and settlement system, known as CHESS, prompting regulators to publicly express their disappointment.
The upgrade is highly complex and involves using blockchain technology, and regulators regard clearing and settlement as a key piece of infrastructure in Australia’s financial system.
After flagging delays in May, the ASX on Wednesday said it was unlikely the upgrade would be completed before late 2024 because more work than previously expected would be needed to meet the exchange’s “scalability and resilience requirements.“
ASX, which appointed new chief executive Helen Lofthouse in June, is bringing in consultancy Accenture to complete an independent review of the new technology, and to identify what needs to be done for the ASX to release a revised timetable for the project.
Both the Reserve Bank and the Australian Securities and Investments Commission (ASIC) said the latest delay was disappointing, but they still expected ASX to replace CHESS as soon as was safely possible.
ASIC chair Joe Longo said it was critical that Accenture’s review provided a high degree of confidence on a new “go-live date” for the project.
“It is very disappointing that there is a further delay to the CHESS Replacement Project,” Longo said. “It is important that the Australian financial system is served well by contemporary infrastructure that is efficient, resilient, reliable and scalable to meet existing and future needs of the market and participants.”
Lofthouse said there had been significant progress with the CHESS project, but it was important to conduct the independent review, given CHESS was a “critical system.”