Since AusNet, the Victorian transmission network operator, was awarded the tender in 2019, it has confronted large-scale community protests by landholders from suburban Melton to potato farming areas near Daylesford, who say it will affect their livelihoods. They want the power lines rerouted or buried, which would add to the costs that would be passed onto retail customers.
Loading
D’Sylva said AusNet was heavily invested in seeking to rebuild trust across affected communities, and he believed it was seeing encouraging signs of progress.
”Once you start behind the eight ball, it’s a little hard to catch up,” he said. “We are doing a lot of work to make sure we get the social licence right in all the communities we work with.“
Following the closure of AGL’s Liddell coal-fired power plant in NSW earlier this year, at least four more coal plants in Victoria, NSW and Queensland are expected to shut down by 2030.
Australian Energy Market Operator chief executive Daniel Westerman, who oversees the nation’s power and gas systems, has been saying the build-out of new generation, storage and transmission lines is happening too slowly to ensure continuous, reliable and affordable electricity supply after coal plants retire.
Transmission links joining the eastern states’ power grids were already “maxing out”, he said, while massive volumes of solar and wind power were having to be curtailed because there was not enough transmission capacity to transport it.
D’Sylva acknowledged there was a “bit of pressure” surrounding the government’s 2030 renewables target, but he said it remained achievable, and AusNet was optimistic Australia could manage the transition.
For the plan to work, industry players and governments would need to “get a wriggle on” in developing or making significant progress on the construction of multiple new transmission links to harness energy from rich wind and solar regions, which are often located far from existing grid infrastructure, he said.
“From our side, we are absolutely committed to building out what’s required,” D’Sylva said.
“We’ve known it’s been needed, but the urgency has just ramped up unbelievably over the last year or so – and what’s been driving that is the retirement of these large coal generators.”
Loading
Westerman implored transmission developers and local stakeholders not to fall into an “us versus them” dichotomy, but stressed that communities being asked to host new power poles and wires deserved to be treated and compensated fairly.
“Communities expect the energy industry to be open with them: no hidden agendas, to explain clearly the situation, not hide behind obscure technical language, to listen, to respond thoughtfully and meaningfully, and to fairly compensate those affected,” he said.